[californiadisasters] Investigation: Massive Outage Took 11 Minutes



Inquiry: Not Enough Coordination Between 5 Power System Operators Affected

By KGTV - San Diego
POSTED: 5:37 pm PDT September 21, 2011
UPDATED: 7:35 pm PDT September 21, 2011

10News is learning new information on Wednesday about the sequence of events that led up to the massive blackout that wiped out power for millions across the region earlier this month.

An investigation by the California Independent System Operator revealed that there was not enough coordination between the five power system operators impacted by the Sept. 8 outage, which left several million people in Orange and San Diego and Imperial Counties as well as part of Mexico and Arizona without power.

"There were 23 major events that occurred within an 11-minute time period within five different power grids," said ISO spokeswoman Stephanie McCorkle.

The outage began on Sept. 8th at 3:27 p.m. when a worker in Arizona accidentally shorted the Southwest Powerlink, which feeds power to Imperial and San Diego Counties.

To compensate for the loss, Imperial County started pulling power from the north, which shut down a line when it overloaded. Then, automated systems began pulling power from the San Diego area. At the same time, a power plant in Mexicali shut down and forced Baja, Mexico to pull power from the San Diego area as well.

Since San Diego was losing power to the east, it started pulling power from Orange County lines. When those lines overloaded, they shut down too.

"The powerlink from the north, coming through San Onofre and the local generation by itself is enough to supply San Diego but it's not near enough to supply San Diego and Imperial County," said San Diego State University professor Murray Jennex.

Jennex said there should have been a barrier in place to prevent Imperial County from tapping into San Diego's power.There was no barrier or if there was, it was not working, so the entire area went black. The entire sequence of events took less than 11 minutes.

"What is not known at this point is why it occurred," said McCorkle.

McCorkle said there are five different power operators that were impacted by the power outage. She admitted the cooperation and communication between the five needs to be improved.

The ISO said it could take months before it has any results from its investigation.

Source: http://www.10news.com/news/29261019/detail.html

--
Check out http://groups.yahoo.com/group/californiadisasters/
Read my blog at http://eclecticarcania.blogspot.com/
My Facebook: http://www.facebook.com/derkimster
Linkedin profile: http://www.linkedin.com/pub/kim-noyes/9/3a1/2b8
Follow me on Twitter @DisasterKim



__._,_.___


Be sure to check out our Links Section at http://groups.yahoo.com/group/californiadisasters/links
Please join our Discussion Group at http://groups.yahoo.com/group/californiadisasters_discussion/ for topical but extended discussions started here or for less topical but nonetheless relevant messages.




Your email settings: Individual Email|Traditional
Change settings via the Web (Yahoo! ID required)
Change settings via email: Switch delivery to Daily Digest | Switch to Fully Featured
Visit Your Group | Yahoo! Groups Terms of Use | Unsubscribe

__,_._,___

No comments:

Post a Comment